If System Variable 405 is enabled for your system, you can create ETC (Estimated Time to Complete) requests if you need additional hours to complete the task.
To use the Tasks submodule, you must have access to
Jobs as defined in the User Access Rights submodule under
Settings.
-
On the main toolbar, click
Jobs
.
-
On the side toolbar of the Jobs screen, click
Jobs List and highlight the job containing the task for which you want to make an ETC request.
-
On the side toolbar of the Jobs screen, click
Tasks.
-
On the Tasks screen, click the Tasks tab.
-
In the grid, highlight a task for which you want to make an ETC request and click
Task Settings
on the tab toolbar.
-
On the Task card, click the Basic Settings tab, then click
.
-
In the Make ETC Request dialog box,
provide the values for the required fields and click
Request.
WorkBook displays the requested ETC hours in the bottom pane of the Tasks tab in the Tasks grid of the job card.