Reset Posting Date of Project Postings to Original Date
Use the Project Posting submodule to reset the post dates of project postings to the original date.
To use the Project Posting submodule, you must have access to Tasks as defined in the User Access Rights submodule under Settings.
To reset the post date of a project posting to the original date:
- On the main toolbar, click Tasks .
- In the left pane of the Tasks screen, click .
- If you have more than one company in your system, use the drop-down list above the grid toolbar to select the company of the project posting whose post date you want to reset to the original date.
- Highlight the type of the project posting whose post date you want to reset to the original date.
- On the side toolbar of the bottom grid, click .
- Highlight the project posting whose post date you want to reset to the original date and click Reset posting date to original date .
- In the Reset Posting Date to Original Date dialog box, select the applicable from post date and to post date.
- Click OK.
Parent Topic: Procedures