Move a Task on Phase to Scrum Sprint (from the Phase Settings Screen)

Use the Tasks submodule to move a task on phase to scrum sprint.

To use Tasks, you must have access to Jobs as defined in User Access Rights under Settings.

To move a task on phase to scrum sprint:

  1. On the main toolbar, click Jobs .
  2. In the left pane of the Jobs page, click Jobs List and highlight the job containing the tasks that you want to move.
  3. In the left pane of the Jobs page, click Tasks.
  4. On the Tasks page, click the Tasks tab.
  5. On the grid toolbar, click the Gantt view.
  6. In the grid, highlight the phase containing the tasks that you want to move and click Phase Settings on the tab toolbar.
  7. On the toolbar of the Phase Settings screen, click Move a Task on Phase to Scrum Sprint .
  8. In the Move Tasks dialog box, select an option and click OK.