Use Partially Settled Purchase Orders in the Follow-Up submodule in the Tasks module to settle partially settled Purchase Orders (POs).
To use Partially Settled Purchase Orders, you must have access to
Tasks as defined in User Access Rights under
Settings.
To settle a partially settled PO:
-
On the main toolbar, click
Tasks
.
-
In the left pane of the Tasks page, click
.
-
Highlight the partially settled PO that you want to settle.
-
In the corresponding
Settle all POs and Set Remaining Amount to 0 field, click
Settle PO and Set Remaining Amount to 0
.
-
In the confirmation dialog box, click
Yes.
WorkBook changes the status of the partially settled purchase order from
Approved to
Settled.
-
If you want to settle all partially settled purchase orders, click
Settle all POs and Set Remaining Amount to 0
and in the confirmation dialog box, click
Yes.