Move Tasks from a Selected Sprint to a Different Sprint

Use the Scrum Board submodule to move tasks from a selected scrum sprint to a different sprint.

To use Scrum Board, you must have access to Scheduling as defined in User Access Rights under Settings.

To move tasks from a selected scrum sprint to a different sprint:

  1. On the main toolbar, click Scheduling .
  2. In the left pane of the Scheduling page, click Schedule Overview > Scrum Board.
  3. Click the Scrum Sprint Overview tab.
  4. On the grid toolbar, click Scrum Sprint Setup .
  5. In the grid, select an item and click Move Tasks from Selection to a Different Sprint on the toolbar.
  6. In the dialog box, provide the values for the required fields and click OK.
  7. Click Close .
    Note: Depending on your access level, you can also perform this action in Settings > Projects & Jobs > Scrum Sprints.