Copy Schedule Data

Use the Tasks submodule to copy schedule data from another job, or from a template.

To use Tasks, you must have access to Jobs as defined in User Access Rights under Settings.

To copy schedule data:

  1. On the main toolbar, click Jobs .
  2. In the left pane of the Jobs page, click Jobs List and highlight the job that contains the schedule data that want to copy.
  3. In the left pane of the Jobs page, click Tasks .
  4. On the Tasks screen, click the Settings tab.
  5. On the grid toolbar, click Copy Schedule Data and select an option.