Show Values of Project Postings in the Amount Columns

Use Project Posting in the Follow-Up submodule in the Tasks module to show the values of project postings in the amount columns.

To use Project Posting, you must have access to Tasks as defined in User Access Rights under Settings.

To show the values of project postings in the amount columns:

  1. On the main toolbar, click Tasks .
  2. In the left pane of the Tasks page, click Follow-Up > Project Posting.
  3. If you have more than one Company in your WorkBook system, use the drop-down list above the grid toolbar to select the Company whose project posting values you want to show in the amount columns.
  4. On the grid toolbar, select the Show Values in the Amount Columns check box.