Update End Dates of Multiple Active Jobs with Overdue End Dates

Use Active Jobs with Overdue End Date in the Follow-Up submodule in the Tasks module to update the end dates of multiple active jobs that have overdue end dates.

To use Active Jobs with Overdue End Date, you must have access to Tasks as defined in User Access Rights under Settings.

To update the end dates of multiple active jobs that have overdue end dates:

  1. On the main toolbar, click Tasks .
  2. In the left pane of the Tasks page, click Follow-Up > Active Jobs with Overdue End Date.
  3. Use the Shift key to highlight the active jobs that have overdue end dates whose end dates you want to update.
  4. On the grid toolbar, click Update End Date for All Selected Jobs .
  5. In the Update End Date dialog box, select a new end date.