Schedule Leave

Use the Edit Date Properties subtask to schedule leave for your Resources.

To request leave, complete the following steps:

  1. Click Time & Expense > Time > Timesheets > Manage Resources Work Schedules to display the Manage Resource Work Schedules screen.
  2. In the Month/Year field, click to select the month for which you want to take leave.
  3. Click to populate the Month/Year results table with the selected month/year.
  4. In the Month/Year results table, select the week of the month that contains the dates for which you want to request leave and click Edit Date Properties.
  5. In the Edit Date Properties subtask, select the date in the Month/Year table for which you want to request leave and click Request Leave. In the Leave section, enter the number of hours in the Hours field.
    Repeat this step for each day you want to request in the currently selected week. Repeat these steps to select days within a different week.
  6. After you have entered hours for each day you want to request, click .
  7. The Month/Year table is updated to reflect the requested or scheduled leave. When you enter leave for a Resource, it is approved automatically.