Reconcile Project Labor Hours Status

Use the Budgeting and Planning reports to reconcile data on the Project Labor Hours Status report.

These reports include the following:

  • Project Status Report

  • Hours Breakdown Report

To reconcile the Costpoint Enterprise Reporting Project Labor Hours Status report with Budgeting and Planning:

  1. Run the Project Labor Hours Status report in Costpoint Enterprise Reporting.
  2. Run the Project Status report in Budgeting and Planning (Project > Supplemental Reports).
  3. Select Latest EAC.
  4. Compare the following:

    Costpoint Enterprise Report

    Budgeting and Planning Report

    ITD Actual Hours + Current Period Actuals

    Labor Hours for Contract to Date – you can expand these fields to verify hours by employee

    Unposted Hours

    Labor Hours for Unposted Time – you can expand these fields to verify hours by employee

    Current Period Actuals

    Labor Hours for Current Period – you can expand these fields to verify hours by employee

  5. Run the Hours Breakdown report in Budgeting and Planning (Project > Budget Development).
  6. Select Latest EAC.
  7. Compare the following:

    Costpoint Enterprise Report

    Budgeting and Planning Report

    Total EAC Hours

    Tot Hrs Bgt

    Current Period Forecast

    Total for monthly column (current period)