Delete the Contents of a Project Plan
If necessary, you can delete the contents of a project plan, including all resource, expense type, and consultant type assignments, the related planned hours or amounts, and the baseline plan, leaving the project with an empty plan.
However, if actual job-to-date (JTD) hours or amounts exist for any of the assignments, those assignments remain in the plan along with the JTD data, though their planned hours and amounts are deleted.
- In the Navigation pane, select .
- Select the project for which you want to delete the plan contents.
- On the Actions bar, click Check Out.
- On the Actions bar, click .
- When a confirmation message displays, click Delete to delete the plan contents.