EAC Exceeds Baseline Dialog Box
Use this dialog box to set up an alert to notify specified employees when the estimate-at-completion (EAC) hours or amounts exceed the established baseline for a project plan.
If the alert is active, it is triggered immediately when EAC for a plan that is selected in the alert criteria for an enabled alert rule exceeds the baseline.
- Related Topics:
- Display the EAC Exceeds Baseline Dialog Box
You display the dialog box from the Resource Planning Alerts form. - Contents of the EAC Exceeds Baseline Dialog Box
Use these fields and options to set up an alert to notify team members when the estimate-at-completion (EAC) hours or amounts exceed the established baseline for the plan.
Parent Topic: Alerts Form