Columns for Labor Plan Summary
You can select the columns to display on your report.
Contents
Field | Description |
---|---|
% Complete (JTD/Planned EAC) | This column displays the percent complete based on estimate-at-completion hours. Vantagepoint calculates the percent complete as follows: JTD Hours / Planned EAC Hours |
% Complete (JTD/Planned) | This column displays the percent complete based on total planned hours from the current plan. Vantagepoint calculates the percent complete as follows: JTD Hours / Planned Hour |
JTD Hours | This column displays the actual job-to-date hours worked. |
Planned – Planned EAC | This column displays the variance between the total planned hours from the current plan and the estimate-at-completion hours: Planned Hours – Planned EAC Hours |
Planned EAC Hours | This column displays the estimate-at-completion hours for the WBS component. The estimate-at-completion hours are the estimated total number of labor hours necessary to complete work. Vantagepoint calculates the planned estimate-at-completion hours as follows: JTD Hours + ETC Hours |
Planned ETC Hours | This column displays the estimate-to-completion hours for the WBS component. The estimate-to-completion hours are the estimated number of planned labor hours necessary to complete the work, starting from the date specified on the Date Basis tab. |
Planned Hours | This column displays the labor hours specified in the plan. |
Row Count | This column displays the row number of a line item. |
Task | This column displays the plan work breakdown structure (WBS) elements for each row of planning data. |
Parent Topic: Labor Plan Summary