Use the Columns tab to select or clear columns, change column sequence, provide new column labels, set column widths, or select number and date formats.
Contents
Field | Description |
Task
|
This column displays the work breakdown structure (WBS) component.
|
Planned Hours
|
This column displays the total planned labor hours for the WBS component from the current plan.
|
JTD Hours
|
This column displays the actual job-to-date hours charged to the WBS component as of the date specified on the Date Basis tab.
|
ETC Hours
|
This column displays the estimate-to-completion hours for the WBS component. The estimate-to-completion hours are the estimated number of planned labor hours necessary to complete the work, starting from the date specified on the Date Basis tab.
|
Planned EAC Hours
|
This column displays the estimate-at-completion hours for the WBS component. The estimate-at-completion hours are the estimated total number of labor hours necessary to complete work. Vision calculates the planned estimate-at-completion hours as follows:
JTD Hours + ETC Hours
|
Planned – EAC
|
This column displays the variance between the total planned hours from the current plan and the estimate-at-completion hours:
Planned Hours – Planned EAC Hours
|
% Complete (JTD/Planned)
|
This column displays the percent complete based on total planned hours from the current plan. Vision calculates the percent complete as follows:
JTD Hours / Planned Hour
|
% Complete (JTD/EAC)
|
This column displays the percent complete based on estimate-at-completion hours. Vision calculates the percent complete as follows:
JTD Hours / Planned EAC Hours
|