When you set up Resource Utilization alerts, Vision notifies specified employees when resource utilization percentages exceed, or fall short of, percentage thresholds that you specify for a plan. This alert is triggered by the process server.
To set up Resource Utilization alerts, complete the following steps:
-
From the Vision Navigation menu, click
.
-
In the
Folders field on the Alerts Configuration form, select
Resource Planning.
-
In the
Alert field, select
Resource Utilization.
-
Select the
Active option to enable the alert throughout Vision; if no rules exist for this alert, the
Active field is disabled.
-
Click
Options to select an existing alert rule or to create a new rule.
If a rule was already assigned to this alert,
<options selected> displays in this field.
-
To remove the option for this alert, delete
<options selected>.
-
Click
Save.