Guidelines for Importing from Microsoft Project

Refer to these guidelines before you import data from Microsoft Project to Vision Planning.

Vision can import both named resources and generic resources.

The default accordion calendar format in Vision is set to Quarter/Month. You may change the calendar scale after data is imported.

Imported time data is converted from minutes in Microsoft Project to hours in Vision.

Task names truncate to 97 characters.

Each Vision plan name defaults to the Microsoft Project file name. After importing into Vision, you can change and save a new plan name.

Vision imports Work from Microsoft Project into Planned Hours, Cost into Planned Cost, Baseline Work into Baseline Hours, and Baseline Cost into Baseline Cost. Vision does not import Actual Work and Actual Cost from Microsoft Project.

When MS ActiveX is used to retrieve assignment rows from MS Project, the rows are returned in the same order as the Resources are entered into the Resource Usage view. This order does not always reflect how Resources are assigned to each Task.