Planning Toolbar
Use the Planning toolbar to perform key actions as you work with a iAccess plan. For example, you can save the plan, publish data, or revert your changes back to the plan's original state.
Contents
Your access to the toolbar options is based on your assigned role's access rights on the Planning tab and iAccess tab on the Roles form in Vision (
). If you don't have the Vision Resource Planning module, then your access is based on your assigned role's access rights on the iAccess tab.Note: These options are enabled and disabled based on the function you are performing. For example, if you make changes to a record and click , that option is disabled until you make additional changes.
Icon | Access Rights Required | Description |
---|---|---|
Show | Access to at least one Planning page | Click the Planning page displayed in this field to select a different page to display. |
Amounts or Hours | Access to the Labor page | Click this field to switch the resource display from hours to amounts or the reverse. This option is only available when the Labor page is displayed. |
Create | Full, Add/Modify | Click Create to create a new iAccess plan for the project. This option only displays when the project has no plan in iAccess or in Vision. |
Convert | Full, Add/Modify | Click Convert to convert the project's Vision plan to an iAccess plan. This option only displays when the project has no plan in iAccess but does have a plan in Vision. |
Check Out | Full, Add/Modify, Modify Only | Click Check Out to check out and make changes to an iAccess plan for the project. This option only displays when the project has an iAccess plan. If someone else has the plan checked out, Check Out is grayed. You can hover over it or tap it to display the name of the person who has it checked out. |
Full, Add/Modify, Modify Only |
Click this icon to save the current iAccess plan information. This action does not publish the plan. This option is available if there are unsaved changes to the current plan. |
|
Full, Add/Modify, Modify Only |
Click this icon to save the current iAccess plan as the baseline. The baseline acts as a snapshot of the plan at a certain point in time and is useful for comparison purposes. You can have only one baseline version for any plan. Any changes you make to the existing baseline will overwrite the previous baseline data. After a baseline exists, this option is available only if your role is allowed to change the baseline. |
|
Full, Add/Modify, Modify Only |
Click this icon to publish the plan and baseline to Vision. This option is available if the current project has an iAccess plan. It saves the current plan and copies its values and the last saved baseline from an unpublished state to a published state. |
|
Full, Add/Modify, Modify Only |
Click this icon to return to the most recently published iAccess plan. This option is available if the current project has an iAccess plan. If no plan information has been published to Vision, the plan is returned to the state that it was in when it was first created. |
|
Full |
Click this icon to clear all of this
iAccess plan's resources and plan entries, including the baseline, from both
iAccess and
Vision. Resources that have JTD charges are not removed.
Note: If the plan has a baseline and you do not have access rights to change the baseline, this option is not available.
|
|
This icon indicates the plan status:
Hover over the icon to display a description of the status. |