Expense Plan Summary Chart
Use the Expense Plan Summary chart on the Expenses page of the Planning tab to view the expenses contract, planned, and job-to-date (JTD) amounts for the WBS element that is selected on the Expenses Planning grid. This summary provides a brief overview of the contract amounts, and the billing and/or cost amounts for direct and reimbursable expenses, as well as for indirect expenses.
Contents
The current project's charge type determines the account (expense) types that can be planned for the project.
As you select different WBS elements on the Expenses Planning grid, amounts on the chart update to reflect the data shown on the grid. The chart also updates to reflect your changes to the plan when you save those changes.
You can hover over or tap a bar on the chart to see the respective amount.
The amounts on this chart display at billing or cost, depending on your selection in Show. Whether both options are available depends on the budget type selected for the plan. If both Billing and Cost options are available, you can switch between them, and the chart's information will update accordingly.
If your firm uses the Multicurrency feature in Vision, the currency in use is indicated in Show next to the Billing and Cost options. The project currency is always used when viewing projects and plans at cost. The currency used when viewing projects and plans at billing is determined by a Vision configuration setting that your system administrator selects. See the Use Project and Billing Currencies online help topic for more information on currencies.
The following table lists the different expense types and amounts that are available to apply to the contract, planned, and JTD amounts on this chart. The values that actually display for a given project depend on what is currently in use for the project.