Change the Labor Resource Assignments Grid View

You can display the resources information in the Labor Resource Assignments grid in either a calendar view or a summary view.

To change the resource grid view, complete the following steps:
  1. In the Labor Planning grid, open the WBS element for which you want to change the view.
  2. Near the left end of the Resource Assignments grid heading row, do one of the following:
    • To switch to the summary view, click and select Summary View. The summary view displays summarized hours or amounts for each resource, including the resource's Baseline, JTD, ETC, and EAC values, and any associated notes entered in iAccess.
    • To switch to the calendar view, and select Calendar View: The calendar view displays the resource's ETC total hours and the planned hours by calendar period.