Contents of the Reassign Dialog Box
Use the fields and options on the Reassign dialog box to transfer all or part of the assigned labor hours from one resource to another.
Field | Description | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Resource and Plan Structure Branch |
The names of the currently assigned resource and of the elements making up the branch of the plan work breakdown structure (WBS) to the level of the assignment display in the upper-left corner of the dialog box. |
||||||||||
Period to Reassign | Click this field and select one of these options:
|
||||||||||
Period | By default, these fields display the start and end dates of the current assignment date range. If you are reassigning multiple assignments, they display the earliest start date and the latest end date of those assignments.
If you are reassigning planned hours for only part of the current assignment date range, enter or select the start date and end date for the reassignment period in these fields. Both dates must be within the original assignment date range. If you are reassigning planned hours for the entire assignment date range, you cannot change the start and end date. |
||||||||||
% to Reassign |
To reassign less than 100 percent of the planned hours for the reassignment period, enter that percentage in this field. The number of hours displayed in Hours to Reassign is updated based on your entry. |
||||||||||
Hours to Reassign |
To reassign fewer than the total number of planned hours for the reassignment period, enter the number of hours in this field. The percentage displayed in % to Reassign is updated based on your entry. |
||||||||||
Maximum Hours | This field displays the maximum number of hours you can reassign for the reassignment period. It is the total number of planned hours for the assignment or assignments that you are reassigning that fall within the reassignment period specified in the Period fields. | ||||||||||
Reassign To Grid | Use the Reassign To grid to locate and select the resource to which you want to reassign the assignment or assignments. To select the resource, click the grid row for that resource.
|
||||||||||
Hard Book |
If you consider the reassignments hard booked, select this checkbox. This checkbox is only available if Vantagepoint is configured to use soft and hard booking and if you have the required security access to hard book assignments. |
||||||||||
Reassign |
To complete the reassignments and close the dialog box, click Reassign. When the reassignment finishes, a completion message displays at the top of the page. Vantagepoint does the following:
|