To assign one or more resources to work on a project, navigate to the Plan form in the Projects hub, select the project, and specify the resource assignments on the Assign Resources to Project dialog box.
In addition to resources that you assign using the procedure below, employees with no planned hours but with JTD hours charged to a work breakdown structure (WBS) element in the plan are assigned automatically and display in the grid as well.
To assign one or more resources to a project:
-
In the Navigation pane, select
.
-
At the top of the Plan form, enter either a complete or partial name or number in the
Find project
lookup field to find and select the project for which you want to assign planned resources.
-
On the Actions bar, click
Check Out.
-
Click the Labor tab.
-
Do one of the following:
- To assign resources to WBS elements in all or many of the branches of the plan structure, hover over the
Level/Resource value in the project-level row in the grid to display the
icon, and click the
.
Vantagepoint displays the entire plan WBS on the Assign Resources to Project dialog box.
- To assign resources to plan elements in just one branch of the plan WBS (a single phase, for example), hover over the
Level/Resource value in the top-level row for that branch in the grid to display the
icon, and click the
.
Vantagepoint displays that branch of the plan WBS on the Assign Resources to Project dialog box.
-
By default, the dialog box displays all employees and generic resources. To restrict the list, do either or both of the following:
- In the top
Search field, select a standard search or a saved custom search.
- In the bottom
Search field, enter one or more search characters to further restrict the list.
Vantagepoint displays a list of resources for which at least one of the following starts with those search characters: employee preferred name, employee first name, employee last name, employee name suffix, employee ID, generic resource name, labor category.
-
In the list of resources, select the checkbox next to those that you want to assign.
-
In
Level column, expand the plan WBS to display the active and inactive WBS elements to which you want to assign the selected resources.
You can assign resources only to the lowest-level WBS elements in each branch of the structure. A
displays next to those elements.
-
In the
Select column, click
next to each of the WBS elements to which you want to assign the selected resources.
The resources are added, as pending assignments, to the list of assigned resources for each of the selected elements. You can expand those elements to display all currently assigned resources.
-
To assign other resources to the project, repeat steps 6 - 9.
-
If you consider the new assignments hard booked, select the
Hard Book checkbox.
This checkbox is available only if
Vantagepoint is configured to use soft and hard booking and if you have the required security access to hard book assignments.
-
To confirm all of the new assignments and close the dialog box, click
Assign.