Remove Dependency Relationships
You can delete dependency relationships on the Schedule tab of the Plan form.
To remove dependencies:
- In the Navigation pane, select .
- Click the Schedule tab.
- On the Actions bar, click Check Out.
-
Do one of the following to remove a dependency relationship:
- Delete the value in the Predecessor field on the left side of the grid.
- Double-click on a Gantt bar and, in the Dependency Details dialog box, click at the end of the row in the Dependencies grid.
Parent Topic: Schedule Project Work