Reschedule Plan Dates Dialog Box
Use the Reschedule Dialog Box to change plan dates or assignment dates for plan rows.
Videos: See related videos below
To reschedule plan dates, you can display this dialog box from the Labor, Expenses, Consultants, or Units tab of the Plan form in the Projects hub or from Project View in Resource Management. This dialog box also displays on the Schedule tab of the Plan form in the Projects hub if you move or drag the Gantt bar of a plan row that has planned hours and/or planned units.
To reschedule labor assignment dates, you can display this dialog box from the Labor tab of the Plan form in the Projects hub or from either Project View or Resource View in Resource Management.
To reschedule unit assignment dates, you can display this dialog box from the Units tab of the Plan form in the Projects hub.
When you enter new dates, you can, if necessary, indicate how you want the schedule change to affect the distribution of planned labor hours or planned unit quantities.
Videos
Title | Description |
---|---|
Learn how to set up the resource planning module, including selecting options for entering and viewing project, opportunity, and resource plans. |
|
Learn how to change the resource assignment dates or duration for an entire plan or for a specific labor assignment. |
|
Learn how to change resource assignments for a project plan. |
|
Learn how to use Project View to review and update resource assignment hours, including estimate-to-complete (ETC) hours, for one or more projects. |
|
Learn how to use Resource View to review and update resource utilization percentages for employees and generic resources assigned to projects. |
|
Learn how to generate reports in Resource Management. You specify which resources are included, the level of the WBS for which you want to see data, and the columns displayed on the report. |
|
Learn how to use the Resource Utilization by Organization report to analyze employee utilization data. |
|
Vantagepoint allows you to set tentatively scheduled labor resource assignments as soft booked and confirmed assignments as hard booked to help manage resource time and workloads. This video demonstrates how to use this feature. |
- Related Topics:
- Display the Reschedule Dialog Box from Resource View
Display the Reschedule Labor Assignments dialog box from Resource View in Resource Management. - Display the Reschedule Dialog Box from Project View
Display either the Reschedule Labor Assignments dialog box or Reschedule Plan Dates dialog box from Project View in Resource Management. - Display the Reschedule Dialog Box from the Projects Hub
You can display the Reschedule Dialog Box from multiple tabs on the Plan form in the Projects hub. - Contents of the Reschedule Plan Dates Dialog Box
Use the Reschedule Plan Dates dialog box to change date ranges for plan rows. Changes to plan dates affect all areas of the plan.