Respread
The Respread process lets you respread budget costs for an entire project at one time or to respread the budget of an individual code of the project. This is useful when the calendar has been changed.
For example, changing the calendar from a monthly to a weekly calendar would require respreading.
When a spread curve is assigned to the resource assignment, Cobra will use it during respread. When Manual spread curve is assigned, or the spread curve is not specified, Cobra uses the existing profile of the resource assignment during respread. The Respread process also generates all calculated costs for the work.
Use the Respread Wizard to run the Respread process. You can also run the Respread process through the API and the Cobra Web Service.
- Related Topics:
- Respread Wizard
To respread budget costs for an entire project at one time or to respread the budget of an individual code of the project, you must complete the information required on each page of the Respread Wizard. - Procedures
Follow the procedures in this section to utilize the Respread process.