Business Validations Page of the Validity Check Wizard

Use this page to select options for validating control accounts, work packages, forecasts, and milestone dates in the project, and perform other data integrity checks on the control accounts or work packages.

Contents

Field Description
Control Accounts and Work Packages that have no resource assignments Select this checkbox if you want to validate whether the control account or work package has resource assignments and if there are costs for the assignments.
Delete Control Accounts/Work Packages with no costs Select this checkbox to delete control accounts or work packages that contain resource assignments without costs entered against them. Control accounts or work packages with no costs include budgets, earned values, actual costs, and forecasts.

This option is enabled if the Control Accounts and Work Packages that have no resource assignments checkbox is selected.

Note: You must have write security permissions to the project to delete it.
Work Package with Milestones has correct Progress Technique Select this checkbox to validate whether or not each work package with milestones has Milestones as the progress technique used.
Forecast dates before status date Select this checkbox to identify invalid forecast dates in the control account or work package and invalid dates selected for the forecast class.

The following are instances when forecast dates are considered invalid:

  • A planned control account or work package has a forecast start date that is before the current status date.
  • A planned control account or work package has a forecast finish date that is before the current status date.
  • A milestone that is in progress or planned has a forecast finish date that is before the current status date.
Slip the Control Account/Work Package dates if the forecast dates are earlier than the status date Select this checkbox to change the invalid forecast start date to the date following the status date. The forecast finish date is also moved by the same number of days to maintain the original duration of the control account or work package.
Note: You must have write permissions to the project to slip the dates.
Control Account dates exactly span Work Package dates Select this option if you want to validate that:
  • The forecast dates for the work package align with the forecast dates for the control account.
  • The baseline dates for the work package align with the baseline dates for the control account.
  • The milestone end dates are within the work package dates.
Adjust Control Account dates to exactly span Work Package dates Select this option if you want to adjust the control account baseline and forecast dates to align to the work package dates, unless the control account date contains control account-level resources beyond the work package dates.
Work Package dates correctly span resource assignment dates Select this option if you want to validate any of the following:
  • Budget resources are within the work package baseline dates.
  • Forecast resources are between the status date and the forecast finish date.
  • Actual resources are prior to the work package actual start date.

    For planned work packages with actual costs: When the Allow posting actual costs to a planned Control Account or Work Package option on Project Properties > Preferences > Actual Costs is cleared, Cobra will display an error message if actual costs exist for planned work packages.

  • All earned value resources are later than the work package actual start date.
  • Earned value records do not exist for planned work packages.
Adjust Work Package dates to span resource assignment dates Select this option if you want to automatically adjust the budget, forecast, and actual work package dates to span their respective resource assignment dates.
Project Audit Log matches Project Value Select this checkbox to identify account records whose project logs do not match the project header and budget values.
Control Account/Work Package dates that are outside of the Project Calendar Select this checkbox to identify Control Account/Work Package start or finish dates (Baseline, Actual, Forecast, Early, Late, and Pending) that fall outside the project calendar dates.
Note: The validity check runs only against the selected master project, not against the sub-projects listed under the master project.