Progress Page of the Integration Wizard-Scheduling Tools
Use this page to select the options for assigning progress techniques to work packages.
Contents
Field | Description |
---|---|
Assign Progress Technique based on Work Package length | Select this option to enable the
Work Packages over two periods in length use Progress Technique field.
Note: If a progress technique is already assigned in Cobra, selecting a new progress technique using this field will not change the progress technique value during the integration.
|
Work Packages over two periods in length use Progress Technique | This field list displays all available progress techniques in Cobra. Select the progress technique you want to use for new work packages longer than two periods.
When you select the Assign Progress Technique based on Work Package length option, Cobra assigns a progress technique to work packages that the import process creates.
|
Use this Progress Technique for all new Work Packages | Select this option to enable the field and select a progress technique. The selected progress technique is assigned to all new work packages created during the import. |
Load Progress Technique from Schedule | Select this option to enable the lookup for all schedule fields. Click
to select a schedule field where you want to map the progress technique.
You can map the following schedule fields:
Cobra imports the progress technique from the Open Plan project's mapped field into the
Progress Technique field under the following conditions:
Cobra does not import the progress technique from the Open Plan project's mapped field into the
Progress Technique field under the following conditions:
If the work package already exists and there is an activity linked to a milestone and the Allow entering milestones regardless of the Progress Technique project preference option is not selected, the progress technique is changed to Milestones. |
Blank Progress Technique use | If the mapped schedule field is empty, Cobra assigns the progress technique based on the value in the Blank Progress Technique use field, which displays a list of all progress techniques in Cobra. Select a progress technique to use if the mapped schedule field is blank. |
Load units to do | Select this option to use the
Units to do field to enter the number of units that remain to be completed. Cobra calculates the earned value as the work package budget multiplied by the number of tasks completed and divided by the value in the
Units to do field. Use this method when the work package contains a predefined number of similar tasks.
Note: Values in this field are imported only for activities assigned with the
Units Complete progress technique.
|
Load milestone weights | Select this option to enable the field and click
to select the schedule field containing milestone weights.
If this option is cleared, Cobra calculates the weight of the milestone based on the budget associated with that milestone. However, this applies only if budget data is imported with the activities; otherwise, milestone weights are set to zero. Values in this field are imported only for activities with the Milestones progress technique. Note: Cobra imports milestone weights up to six decimal places. If it exceeds, Cobra will round the milestone weight value to six decimal places.
Attention: For more information on how milestone weights are calculated, see
Milestones/Steps.
|
Video
Title | Description |
---|---|
Importing the Progress Technique from the Schedule | View this video to explore the many options for choosing the progress technique while importing from the schedule. |