Filter Page of the Integration Wizard-Files
Use this page to define the data to be imported.
Contents
Field | Description |
---|---|
Criteria | Select one of the following options:
If you are loading budget resource assignments, only the budget totals, including the project-level budget totals, are updated. If you are loading forecast resource assignments, only the EAC totals, including the project-level EAC totals, are updated. Note: If you select
Control Account or
Work Package, the
Selection field is enabled.
|
Selection | Click
to select a schedule field mapped as a Control Account or Work Package field on the Schedule Mapping page. You can also select one of the following options:
|
Delete only items that satisfy the selection criteria | Select this option to delete only items from Cobra that meet the criteria selected.
If Cobra is made up of multiple single projects loaded through the Integration Wizard, and a single project is being loaded, Cobra will only consider deleting items that are not in the schedule if the code field contains the name of the project being loaded. You can either enter the project name specifically in the Equals field, or you can enter the project name generically by using the reserved value <ProjectName>. Note: This option considers the deletion filter on the Change Control page and only deletes items within the criterion that matches the filter. This option displays only when importing activity data into an existing project.
|
Load only schedule activities that do not exist in Cobra | Select this option to import only new data and to ignore any existing data so that previously imported data remains the same. |
Load only data for Control Accounts that already exist in Cobra | Select this option to import only data previously imported and to ignore any new information. You cannot select both the Load only schedule activities that do not exist in Cobra and Load only data for Control Accounts that already exist in Cobra checkboxes at the same time. |