Move Work Package Dialog Box
Use this dialog box to create a new work package by moving an existing one from one location to another.
This feature is similar to copying a work package, except that when you move a work package, Cobra deletes that work package from its original location.
Contents
Field | Description |
---|---|
Move From | These fields display the control account and work package containing the information that will be moved. You cannot modify these fields. |
Move To | Use these fields to specify the settings for the target control account. |
Control Account | Select the control account to which Cobra will copy the selected work package. Click
![]() You can copy a work package to the same control account or to a different control account. |
Work Package | Use this field to enter a name for the new work package. When you created the project using the New Project Wizard and assigned a code file to the work package field, click
![]() |
- Related Topics:
- Display the Move Work Package Dialog Box
Display the Move Work Package dialog box to create a new work package by moving an existing one from one location to another using a different work package name.
Parent Topic: Dialog Boxes (Spreadsheet Pane of the Project View)