Copy Down Threshold Values to Child Resources

Use the Copy Down Thresholds utility to copy the threshold values of a selected resource to its child resources.

To copy down threshold values to child resources:

  1. Display the Resource view of the resource file that you want to update.
  2. In the Resource view, click the resource whose threshold values you want to copy to the child resources and take one of the following actions:
    • In the Codes group on the Edit tab, click Copy Thresholds.
    • Right-click the Resources grid and select Copy Thresholds.
    The Copy Down Thresholds option is available if you select a parent resource that has child resources and defined threshold values.
  3. Click Yes to copy the threshold values of the parent resource to its child resources.
    If your resource file has more than two levels, applying the Copy Down Thresholds feature to the top-most resource will copy the threshold values for that resource to all the resources in the lower levels.