Use the Calculations tab of the Resource view to add calculations to a resource or child resource.
To add a calculation to a resource:
-
Display the Resource view of the resource file that you want to update.
-
In the Resources grid of the Resource view, select a resource or child resource.
You must select a resource that has a result assignment.
Note: Resources that already have result assignments are denoted by
.
-
Select the Calculations tab.
-
In the Calculation pane of the Calculations tab, select the result for which you want to set up a calculation.
-
In the Source Results pane, select the results that you want to use in the calculation.
For example, if you selected G&A on the Calculation grid, you can calculate the G&A (General and Administrative) result as a function of the DIRECT and OVERHEAD results.
G&A = (DIRECT + OVERHEAD) x G&A rate
-
Click
on the Quick Access toolbar to save the changes.