Use the Calculations tab of the Resource view to copy calculations from a resource to another resource.
To copy calculations from another resource:
-
Display the Resources view.
-
On the Resources grid of the Resource view, select the resource to which Cobra will copy the calculations. You must select a resource that does not have a result assignment.
Note: Resources that already have result assignments are denoted by
.
-
Select the Calculations tab.
-
Display the Copy Resource Calculation dialog box by completing one of the following steps:
- In the
Resources group on the Edit tab, click
Copy Calculations.
- Right-click the Calculation pane on the Calculations tab and select
Copy Calculations on the shortcut menu.
-
In the Copy Resource Calculation dialog box, click
to select the resource from which you want to copy the calculations.
-
Click
OK.
Cobra copies the calculations to the resource that you selected on the Resources grid.
-
Click
on the Quick Access toolbar to save the changes.