Procedures
Follow the procedures in this section to utilize the Calculate Progress process.
- Related Topics:
- Assign a Progress Technique to a Work Package
Use the General tab of the Project view to assign a progress technique to a work package. - Add a Second Earned Value Class to Your Project
You can add a second earned value class to a project. This is useful when you are tracking professional services. - Select the Level at Which to Capture Actual Costs
Use the Files tab of the Project Properties dialog box to change the level at which actual costs are captured. - Select the Earned Value Method
Use the Earned section of the Preferences tab of the Project Properties dialog box to select the method for calculating the earned value for a project. - Calculate Progress
Use the Calculate Progress Wizard to calculate the earned value for a project or group of projects.
Parent Topic: Calculate Progress