Update EAC Dialog Box
Use this dialog box to manually update the forecast values for a control account or work package.
The Update EAC dialog box is only available if you set the Scale Retain EAC field on the Forecast Preferences tab of the Project Properties dialog box to Hours, Currency, or Hours and Currency.
If you set the Scale Retain EAC field to Currency or Hours, the Update EAC dialog box displays with a field for updating the value for Hours or Currency. If you set Scale Retain EAC field to Hours and Currency, the Update EAC dialog box displays with two fields for updating the values for both Hours and Currency.
You must have access control that is greater than read-only to use the Update EAC utility.
Contents
Field | Description |
---|---|
Old value | This field displays the old value for the Hours or Currency. You cannot change the value in this field. |
New value | Use this field to enter the new value for the Hours or Currency. |
- Related Topics:
- Display the Update EAC Dialog Box
Display the Update EAC dialog box to manually update the forecast values for a control account or work package.