Synchronize Status Dates
Use the Synchronize button on the General tab of the Project Properties dialog box to change the status date if TODATE is not properly labeled at project creation time without advancing the calendar.
Note: This option does not have all the functionality of advancing the calendar and should not be used as an alternative to the advance calendar function once the project is underway.
To synchronize status dates:
- Display the Project Properties dialog box and select the General tab.
- Click Synchronize.
- Click Apply to save the changes.
Parent Topic: Procedures
How to...