Criteria Page of the Reclass Wizard

Use this page to select the portion of the project that you want to reclass.

Contents

Field Description
Criteria Use this field to select one of the following options:
  • Total Project
  • Control Account
  • Work Package
  • Control Account Key Fields
  • Work Package Field
  • Resource
  • Resource Assignment
  • Control Account Codes 1 to 20
  • Work Package Codes 1 to 20
  • CAM
  • Work Package Manager

If you want to reclass the entire project, select Total Project.

Note: The options listed in this field are based on the control account, work package, and resource assignment structures that you define on the Fields tab of the Project Properties dialog box.
Selection This field is enabled if you select a criterion other than Total Project in the Criteria field. Click to display a dialog box that lists all valid options based on the selected criterion.
For example, if you select Control Account, the Control Account Lookup dialog box displays, showing all control accounts used in the selected project.
Include all children This checkbox is available if you select a code validated with a code file in the Selection field. Selecting this checkbox instructs Cobra to run the Reclass process against any code assignments with the selected code and its children.
For example, if you select WBS code 1.1 in the Selection field and then select the Include all children checkbox, control accounts and/or work packages with a code assignment of 1.1 or any child codes, such as 1.1.1 and 1.1.2 will be included in the Reclass process.