Calculate Forecast Spread by Budget
A set of examples may help demonstrate how Cobra calculates forecast spread according to the current spread.
Assume that you have the following budgeted and forecast costs before statusing:
Periods | 1 | 2 | 3 | 4 | 5 | Total |
---|---|---|---|---|---|---|
Budget | 100 | 200 | 300 | 200 | 200 | 1000 |
ETC | 100 | 200 | 300 | 200 | 200 | 1000 |
After one period, assume that ETC has been calculated as follows:
ETC = BAC Earned Value = 1000 - 50 = 950
This results in the following cost data:
Periods | 1 | 2 | 3 | 4 | 5 | Total |
---|---|---|---|---|---|---|
Budget | 100 | 200 | 300 | 200 | 200 | 1000 |
Earned Value | 50 | 50 | ||||
Actual Costs | 100 | 100 | ||||
ETC | 211 | 317 | 211 | 211 | 950 |
Now, if the estimated finish date for the work package had been pushed back one period (to take the poor performance into account), the spread would be:
Periods | 1 | 2 | 3 | 4 | 5 | 6 | Total |
---|---|---|---|---|---|---|---|
Budget | 100 | 200 | 300 | 200 | 200 | 1000 | |
ETC | 95 | 190 | 285 | 190 | 190 | 950 |
Note, however, that the profile used depends on how much has been earned. Because the earned value was less than the amount of the first period budget, the entire budget profile was used. If, however, the full amount had been earned, the profile used would have been generated from the last four periods of budget. For example, assume a performance factor of 1 and the following cost data:
Periods | 1 | 2 | 3 | 4 | 5 | 6 | Total |
---|---|---|---|---|---|---|---|
Budget | 100 | 200 | 300 | 200 | 200 | 1000 | |
Earned Value | 100 | 100 | |||||
Actual Costs | 120 | 120 |
- Period 2 .222
- Period 3 .333
- Period 4 .222
- Period 5 .222
- Period 2 .222
- Period 3 .555
- Period 4 .777
- Period 5 1.0
- First spread point
- Factor= 4 * (1/5) =.8
- Integer= 0
- Modulus = .8
- Percent= 0 + (.8 * (.222 - 0)) = .178
- Second spread point
- Factor= 4 * (2/5) = 1.6
- Integer= 1
- Modulus = .6
- Percent = .222 + (.6 * (.555 - .222)) = .422
- Third spread point
- Factor= 4 * (3/5) = 2.4
- Integer = 2
- Modulus= .4
- Percent= .555 + (.4 * (.777 - .555)) = .644
- Fourth spread point
- Factor = 4 * 4/5 = 3.2
- Integer = 3
- Modulus= .2
- Percent = .777 + (.2 * (1 - .777)) = .821
- Fifth spread point
- Factor= 4 * (5/5) = 4
- Integer= 4
- Modulus= 0
- Percent= 1
These spread points are then multiplied by the ETC amount to get cumulative spread values for the ETC, and the interval values are then obtained by subtraction of the previous value:
Periods | 1 | 2 | 3 | 4 | 5 | 6 | Total |
---|---|---|---|---|---|---|---|
Budget | 100 | 200 | 300 | 200 | 200 | 1000 | |
ETC | 160 | 220 | 200 | 160 | 160 | 900 |