Assign Sub-Projects to a Master Project

Use the Sub-Projects tab of the Project Properties dialog box to assign sub-projects to a master project.

To assign sub-projects to a master project:

  1. Display Project Properties dialog box and select the Sub-Projects tab.
  2. Click Add to open the Project Lookup dialog box.
  3. Select the projects that you want to add as sub-projects to the master project.
  4. Click Select to add the selected projects to the master project.