Load an Import File with Activity and Resource Assignment Data

Run the Integration Wizard to load an import file with activity and resource assignment data.

To load an import file with activity and resource assignment data:

  1. Click the Integration tab.
  2. In the Import group, click File.
  3. On the Integration Configuration page, click Open an existing configuration to load an existing configuration or click Create a new configuration to create a new one (for example, a budget configuration).
  4. On the Action Selection page, select the appropriate data based on the import file you are loading.
  5. On the Project Selection page, select the file that contain the data you are loading and the Cobra project you want to integrate with.
  6. Compete the succeeding pages of the Integration Wizard-Scheduling Tools and Files.