Behavior of the Options
This section describes the behavior of Integration Wizard Preferences option and its corresponding option on the process wizard page.
Allow Loading Forecast in the Current Status Period
Integration Wizard Preferences Tab Option | Resource Assignments Page of the Integration Wizard Option | ||
---|---|---|---|
Selected | Secure | New Configuration | Existing Configuration |
Yes | No | Yes ¦ Enabled | Follows the selection in the configuration file |
Yes | Yes | Yes ¦ Disabled | Follows the selection on Integration Wizard Preferences tab |
No | No | No ¦ Enabled | Follows the selection on Integration Wizard Preferences tab |
No | Yes | No ¦ Disabled | Follows the selection in the configuration file |
Delete Milestones No Longer in the Schedule
Integration Wizard Preferences Tab Option | Change Control Page of the Integration Wizard Option | ||
---|---|---|---|
Selected | Secure | New Configuration | Existing Configuration |
Yes | No | Yes ¦ Enabled | Follows the selection in the configuration file |
Yes | Yes | Yes ¦ Disabled | Follows the selection on Integration Wizard Preferences tab |
No | No | No ¦ Enabled | Follows the selection on Integration Wizard Preferences tab |
No | Yes | No ¦ Disabled | Follows the selection in the configuration file |
Notes
- Yes indicates that the checkbox is selected.
- No indicates that the checkbox is cleared.
- Enabled means you can still select or clear the checkbox.
- Disabled means you can no longer select or clear the checkbox.
Parent Topic: Integration Wizard Preferences