Copy Element of Cost Value to Child Resources

Use this procedure to copy the element of cost value attached to a parent resource to its child resources.

To copy element of cost value to child resources:

  1. Display the Resource view of the resource file that you want to update.
  2. In the Resource view, click a parent resource and take one of the following actions:
    • In the Codes group on the Edit tab, click Copy Element of Cost.
    • Right-click the Resources grid and select Copy Element of Cost.
    Note: The Copy Element of Cost option is enabled only for resources with child resources.
  3. Click Yes when the confirmation message displays.
  4. Click to save your changes.