Absolute Mapping
The way Acumen Risk assigns risk impact across multiple activities depends on whether or not you use absolute mapping.
- When you use no absolute mapping, risk is spread across multiple activities. If you map a risk event to a parent activity with no absolute mapping, the impact of the risk event gets spread across all children activities and is pro-rated based on the relative duration/cost of the children.
- When you use absolute mapping, total risk is allocated to each activity. If you map a risk event to a parent activity and use absolute mapping, the total impact of the risk event gets allocated to each child activity. After selecting the Absolute Column check box, you can see the changes in the Minimum and Maximum Duration columns on the Mappings tab.
Example of Spreading Risk vs Allocating Total Risk to Multiple Activities
You have the following activities:
Activity | Remaining Duration |
---|---|
Activity A | 17d |
Activity B | 65d |
You map a high probability risk with a very high schedule impact to Activity A. In the Risk Matrix Template, Very High Impact is set to 120-150 days.
Activity | Remaining Duration | Minimum Duration | Maximum Duration |
---|---|---|---|
Activity A | 17d | 120d | 150d |
If you map that same risk to Activity B, the risk impact is spread over the two activities.
Activity | Remaining Duration | Minimum Duration | Maximum Duration |
---|---|---|---|
Activity A | 17d | 25d | 31d |
Activity B | 65d | 95d | 119d |
If you map the risk to multiple activities and click the Absolute Mapping option next to the risk, the entire risk impact is allocated to each activity.
Activity | Remaining Duration | Minimum Duration | Maximum Duration |
---|---|---|---|
Activity A | 17d | 120d | 150d |
Activity B | 65d | 120d | 150d |