Display the Cleanse Schedule Dialog Box
Use the Cleanse Schedule dialog box to specify how you want the schedule to be cleansed.
To display the Cleanse Schedule dialog box, complete the following steps:
- On the S1 // Projects tab, in the Projects pane, select the project or snapshot whose schedule you want to cleanse.
- In the Scenario Generation group, click Cleanse Schedule. The Cleanse Schedule dialog box displays.