Display a Second Bar on the Gantt Chart
Display a second (bottom) bar on the Gantt chart. This enables the Bottom Bar options on the SmartGantt Configuration dialog box.
To display a bottom activity bar on the Gantt chart, complete the following steps:
- Select the S1 // Projects tab.
- In the Activities group, click the SmartGantt drop-down arrow.
- Hover over the Bottom Bar command to see the drop-down menu and select the type of data that you want the bottom bar to display. The bottom bar command is highlighted and the bottom bar for each activity displays in the Gantt chart.