Assign a P6 Baseline to a P6 Schedule
Assign a P6 baseline to a P6 schedule. Assigning a P6 baseline to a P6 schedule allows you to compare baseline data with the current schedule.
To assign a P6 baseline to a P6 schedule, complete the following steps:
- Select the S1 // Projects tab.
-
Do one of the following:
- In the Projects pane, right-click on the P6 project and select Assign Baseline.
- Select the P6 project in the Projects pane and click .
- On the Open dialog box, select the P6 XER that you want to set as the baseline project. After it is assigned, a black B () displays on the Primavera P6 file icon in the Projects panel of the workbook to show that it has an assigned baseline.
- Import the project data to import both the project and baseline files together.
Baselines can be reassigned, assigned, added, or deleted by right-clicking on the Primavera project.