Project Fields on the Metrics Tab
Some project level fields get automatically imported during a project import. These fields are automatically exposed and can be used within metric formulas.
When a metric is calculated that contains a project field reference, the specific project field value for the activity in question is used. A single metric calculation may contain activities from multiple projects. In this instance, the appropriate project level field value will be used for each activity (for example, "time now" may be different for each of the projects).
Project fields include:
- Project Start [ProjectStart]
- Project Finish[ProjectFinish]
- Project Time Now [ProjectTimeNow]