Standard Field Mappings

Acumen includes standard field mappings for each of the supported platforms.

These are listed below. You can create additional custom field mappings using the Fields tab.

Acumen Field Microsoft Project / Project Server Primavera P6 Primavera Risk Deltek Cobra Deltek Open Plan UN/CEFACT Safran
Activity Status Status Activity Status Calculated NA Progress Type Calculated NA
Activity Type Calculated Activity Type Task Type Calculated Activity Type ProjectScheduleTask.TypeCode Calculated
Actual Cost Actual Cost Calculated Cost[Actual] NA Calculated NA Calculated
Actual Duration Actual Duration Actual Duration NA NA NA NA Calculated
Actual Finish Actual Finish Actual Finish Actual Finish NA Actual Finish ActualScheduledBasePeriod.Finish Calculated
Actual Start Actual Start Actual Start Actual Start NA Actual Start ActualScheduledBasePeriod.Start Calculated
ACWP (AC) ACWP ACWP ACWP (AC) NA NA
Baseline Finish Baseline Finish Planned Finish Baseline Finish NA Baseline Finish TargetScheduledBasePeriod.Finish Baseline Early Finish
Baseline Start Baseline Start Planned Start Baseline Start NA Baseline Start TargetScheduledBasePeriod.Start Baseline Early Start
Baseline Work Baseline Work Budgeted Labor Units Calculated NA NA NA NA
BCWP (EV) BCWP BCWP (EV) Calculated BCWP (EV) Calculated NA NA
BCWS (PV) BCWS Calculated NA BCWS (PV) NA NA NA
Budget Cost Baseline Cost Calculated Cost[Budget] NA Calculated NA NA
CAM-EAC NA NA NA CAM-EAC NA NA NA
Critical Critical Critical Critical NA Critical_Activity ProjectScheduleTask.CriticalPathIndicator Calculated
Description Name Activity Name Description Description Activity Desc. ProjectScheduleTask.Description Description
EAC EAC EAC NA EAC NA NA NA
Early Finish Early Finish Early Finish Early Finish NA Early Finish EarliestScheduledBasePeriod.Finish NA
Early Start Early Start Early Start Early Start NA Early Start EarliestScheduledBasePeriod.Start Early Start
ETC NA NA NA ETC NA NA NA
Finish Finish Finish Finish Calculated Early Finish CurrentScheduledBasePeriod.Finish Calculated
Free Float Free Float Free Float Free Float NA Free Float Free Float Free Float
ID ID Activity ID ID ID Activity ID ProjectScheduleTask.Name Activity Name
Late Start Late Start Late Start Late Start NA Late Start Late Start Late Start
Late Finish Late Finish Late Finish Late Finish NA Late Finish Late Finish Late Finish
LIKELY NA NA NA LIKELY NA NA NA
Longest Path Critical Longest Path Critical NA Critical NA Calculated
MOD NA NA NA MOD NA NA NA
Number of Lags Calculated Calculated Calculated NA Calculated ProjectScheduleTaskRelationship.LagTimeMeasure NA
Number of Leads Calculated Calculated Calculated NA Calculated Calculated NA
Number of FF Predecessors Calculated Calculated Calculated NA Calculated Calculated NA
Number of Predecessors Calculated Calculated Calculated NA Calculated Calculated NA
Number of SF Predecessors Calculated Calculated Calculated NA Calculated Calculated NA
Number of SS Predecessors Calculated Calculated Calculated NA Calculated Calculated NA
Number of Successors Calculated Calculated Calculated NA Calculated Calculated NA
Original Duration Duration Original Duration Original Duration NA Original Duration TotalDurationMeasure Duration
OTB NA NA NA OTB NA NA NA
P50 Cost NA NA P50 Cost NA NA NA NA
P50 Finish NA NA P50 Finish NA NA NA NA
P50 Start NA NA P50 Start NA NA NA NA
P80 Cost NA NA P80 Cost NA NA NA NA
P80 Finish NA NA P80 Finish NA NA NA NA
P80 Start NA
Percent Complete % Complete Calculated Percent Complete NA Calculated ProjectScheduleTask.CalculatedCompletionPercent NA
PLAN_ACC NA NA NA PLAN_ACC NA NA NA
Primary Constraint Constraint Type Primary Constraint Primary Constraint NA Calculated Primary Constraint Calculated
Primary Constraint Date Constraint Date Primary Constraint Date Primary Constraint Date NA Calculated Primary Constraint Date Calculated
Project Finish Finish Date Finish Data Date NA Scheduled Finish NA NA
Project Start Start Date Start Start NA Project Start NA NA
Project Time Now Status Date Data Date Finish NA Time Now NA NA
Remaining Cost Remaining Cost Calculated Cost[Remaining] NA ETC NA Calculated
Remaining Duration Remaining Duration Remaining Duration Remaining Duration NA Computed Remaining Dur. ProjectScheduleTask.RemainingDurationMeasure Remaining Duration Analyzed
REPLAN NA NA NA REPLAN NA NA NA
Risk Input - Duration Description NA NA Calculated NA NA NA
Risk Input - Duration LowerPcent NA NA Calculated NA NA NA NA
Risk Input - Duration Max NA NA Risk Input - Duration Maximum NA NA NA NA
Risk Input - Duration Mean NA NA Risk Input - Duration Mean NA NA NA NA
Risk Input - Duration Min NA NA Risk Input - Duration Minimum NA NA NA NA
Risk Input - Duration MostLikely NA NA Risk Input - Duration MostLikely NA NA NA NA
Risk Input - Duration MostlikelyPcent NA NA Calculated NA NA NA NA
Risk Input - Duration Notes NA NA Risk Input - Duration Notes NA NA NA NA
Risk Input - Duration Risk Distribution NA NA Calculated NA NA NA NA
Risk Input - Duration RiskFunction NA NA Calculated NA NA NA NA
Risk Input - Duration RiskId NA NA Calculated NA NA NA NA
Risk Input - Duration RiskOn NA NA Calculated NA NA NA NA
Risk Input - Duration Shape NA NA Calculated NA NA NA NA
Risk Input - Duration StdDeviation NA NA Calculated NA NA NA NA
Risk Input - Duration UpperPcent NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Description NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Notes NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskFunction NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskId NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskOn NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links Description NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links Notes NA NA Risk Input - Probabilistic Links Notes NA NA NA NA
Risk Input - Probabilistic Links RiskFunction NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links RiskId NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links RiskOn NA NA Calculated NA NA NA NA
Risk Input - Task Existence Description NA NA Calculated NA NA NA NA
Risk Input - Task Existence Notes NA NA Risk Input - Task Existence Notes NA NA NA NA
Risk Input - Task Existence RiskFunction NA NA Risk Input - Task Existence Function NA NA NA NA
Risk Input - Task Existence RiskId NA NA Calculated NA NA NA NA
Risk Input - Task Existence RiskOn NA NA Calculated NA NA NA NA
Risk Input - Task Existence Probability NA NA Risk Input - Task Existence NA NA NA NA
Risk Output - CostSensitivity NA NA Risk Output - CostSensitivity NA NA NA NA
Risk Output - CostStdDeviation NA NA Risk Output - CostStdDeviation NA NA NA NA
Risk Output - CriticalityIndex NA NA Risk Output - CriticalityIndex NA NA NA NA
Risk Output - DurationCruciality NA NA Risk Output - Duration Cruciality NA NA NA NA
Risk Output - DurationStdDeviation NA NA Risk Output - DurationStdDeviation NA NA NA NA
Risk Output - DurationSensitivity NA NA Risk Output - DurationSensitivity NA NA NA NA
Risk Output - MeanCost NA NA Risk Output - MeanCost NA NA NA NA
Risk Output - MeanDuration NA NA Risk Output - MeanDuration NA NA NA NA
Risk Output - MeanFinish NA NA Risk Output - MeanFinish NA NA NA NA
Risk Output - MeanStart NA NA Risk Output - MeanStart NA NA NA NA
Risk Output - PercentageTaskExisted NA NA Risk Output - % Iterations Existed NA NA NA NA
Risk Output - ScheduleSensitivityIndex NA NA Risk Output - ScheduleSensitivityIndex NA NA NA NA
Secondary Constraint NA Secondary Constraint NA NA Calculated Secondary Constraint Calculated
Secondary Constraint Date NA Secondary Constraint Date NA NA Calculated Secondary Constraint Date Calculated
Start Start Start Start Start Early Start CurrentScheduledBasePeriod.Start Calculated
Total Cost Cost Calculated Cost[Total] NA Calculated NA NA
Total Float Total Slack Total Float TotalFinshFloat NA Total Float ProjectScheduleTask.TotalFloatDurationMeasure Total Float
WBS Code Outline Number WBS Work Breakdown Structure WBS Code NA NA NA
WBS Name Outline Number WBS Name Work Breakdown Structure WBS Name NA NA NA
WORST NA NA NA WORST NA NA NA