Standard Field Mappings
Acumen includes standard field mappings for each of the supported platforms.
These are listed below. You can create additional custom field mappings using the Fields tab.
Acumen Field | Microsoft Project / Project Server | Primavera P6 | Primavera Risk | Deltek Cobra | Deltek Open Plan | UN/CEFACT | Safran |
---|---|---|---|---|---|---|---|
Activity Status | Status | Activity Status | Calculated | NA | Progress Type | Calculated | NA |
Activity Type | Calculated | Activity Type | Task Type | Calculated | Activity Type | ProjectScheduleTask.TypeCode | Calculated |
Actual Cost | Actual Cost | Calculated | Cost[Actual] | NA | Calculated | NA | Calculated |
Actual Duration | Actual Duration | Actual Duration | NA | NA | NA | NA | Calculated |
Actual Finish | Actual Finish | Actual Finish | Actual Finish | NA | Actual Finish | ActualScheduledBasePeriod.Finish | Calculated |
Actual Start | Actual Start | Actual Start | Actual Start | NA | Actual Start | ActualScheduledBasePeriod.Start | Calculated |
ACWP (AC) | ACWP | ACWP | ACWP (AC) | NA | NA | ||
Baseline Finish | Baseline Finish | Planned Finish | Baseline Finish | NA | Baseline Finish | TargetScheduledBasePeriod.Finish | Baseline Early Finish |
Baseline Start | Baseline Start | Planned Start | Baseline Start | NA | Baseline Start | TargetScheduledBasePeriod.Start | Baseline Early Start |
Baseline Work | Baseline Work | Budgeted Labor Units | Calculated | NA | NA | NA | NA |
BCWP (EV) | BCWP | BCWP (EV) | Calculated | BCWP (EV) | Calculated | NA | NA |
BCWS (PV) | BCWS | Calculated | NA | BCWS (PV) | NA | NA | NA |
Budget Cost | Baseline Cost | Calculated | Cost[Budget] | NA | Calculated | NA | NA |
CAM-EAC | NA | NA | NA | CAM-EAC | NA | NA | NA |
Critical | Critical | Critical | Critical | NA | Critical_Activity | ProjectScheduleTask.CriticalPathIndicator | Calculated |
Description | Name | Activity Name | Description | Description | Activity Desc. | ProjectScheduleTask.Description | Description |
EAC | EAC | EAC | NA | EAC | NA | NA | NA |
Early Finish | Early Finish | Early Finish | Early Finish | NA | Early Finish | EarliestScheduledBasePeriod.Finish | NA |
Early Start | Early Start | Early Start | Early Start | NA | Early Start | EarliestScheduledBasePeriod.Start | Early Start |
ETC | NA | NA | NA | ETC | NA | NA | NA |
Finish | Finish | Finish | Finish | Calculated | Early Finish | CurrentScheduledBasePeriod.Finish | Calculated |
Free Float | Free Float | Free Float | Free Float | NA | Free Float | Free Float | Free Float |
ID | ID | Activity ID | ID | ID | Activity ID | ProjectScheduleTask.Name | Activity Name |
Late Start | Late Start | Late Start | Late Start | NA | Late Start | Late Start | Late Start |
Late Finish | Late Finish | Late Finish | Late Finish | NA | Late Finish | Late Finish | Late Finish |
LIKELY | NA | NA | NA | LIKELY | NA | NA | NA |
Longest Path | Critical | Longest Path | Critical | NA | Critical | NA | Calculated |
MOD | NA | NA | NA | MOD | NA | NA | NA |
Number of Lags | Calculated | Calculated | Calculated | NA | Calculated | ProjectScheduleTaskRelationship.LagTimeMeasure | NA |
Number of Leads | Calculated | Calculated | Calculated | NA | Calculated | Calculated | NA |
Number of FF Predecessors | Calculated | Calculated | Calculated | NA | Calculated | Calculated | NA |
Number of Predecessors | Calculated | Calculated | Calculated | NA | Calculated | Calculated | NA |
Number of SF Predecessors | Calculated | Calculated | Calculated | NA | Calculated | Calculated | NA |
Number of SS Predecessors | Calculated | Calculated | Calculated | NA | Calculated | Calculated | NA |
Number of Successors | Calculated | Calculated | Calculated | NA | Calculated | Calculated | NA |
Original Duration | Duration | Original Duration | Original Duration | NA | Original Duration | TotalDurationMeasure | Duration |
OTB | NA | NA | NA | OTB | NA | NA | NA |
P50 Cost | NA | NA | P50 Cost | NA | NA | NA | NA |
P50 Finish | NA | NA | P50 Finish | NA | NA | NA | NA |
P50 Start | NA | NA | P50 Start | NA | NA | NA | NA |
P80 Cost | NA | NA | P80 Cost | NA | NA | NA | NA |
P80 Finish | NA | NA | P80 Finish | NA | NA | NA | NA |
P80 Start | NA | ||||||
Percent Complete | % Complete | Calculated | Percent Complete | NA | Calculated | ProjectScheduleTask.CalculatedCompletionPercent | NA |
PLAN_ACC | NA | NA | NA | PLAN_ACC | NA | NA | NA |
Primary Constraint | Constraint Type | Primary Constraint | Primary Constraint | NA | Calculated | Primary Constraint | Calculated |
Primary Constraint Date | Constraint Date | Primary Constraint Date | Primary Constraint Date | NA | Calculated | Primary Constraint Date | Calculated |
Project Finish | Finish Date | Finish | Data Date | NA | Scheduled Finish | NA | NA |
Project Start | Start Date | Start | Start | NA | Project Start | NA | NA |
Project Time Now | Status Date | Data Date | Finish | NA | Time Now | NA | NA |
Remaining Cost | Remaining Cost | Calculated | Cost[Remaining] | NA | ETC | NA | Calculated |
Remaining Duration | Remaining Duration | Remaining Duration | Remaining Duration | NA | Computed Remaining Dur. | ProjectScheduleTask.RemainingDurationMeasure | Remaining Duration Analyzed |
REPLAN | NA | NA | NA | REPLAN | NA | NA | NA |
Risk Input - Duration Description | NA | NA | Calculated | NA | NA | NA | |
Risk Input - Duration LowerPcent | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration Max | NA | NA | Risk Input - Duration Maximum | NA | NA | NA | NA |
Risk Input - Duration Mean | NA | NA | Risk Input - Duration Mean | NA | NA | NA | NA |
Risk Input - Duration Min | NA | NA | Risk Input - Duration Minimum | NA | NA | NA | NA |
Risk Input - Duration MostLikely | NA | NA | Risk Input - Duration MostLikely | NA | NA | NA | NA |
Risk Input - Duration MostlikelyPcent | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration Notes | NA | NA | Risk Input - Duration Notes | NA | NA | NA | NA |
Risk Input - Duration Risk Distribution | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration RiskFunction | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration RiskId | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration RiskOn | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration Shape | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration StdDeviation | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Duration UpperPcent | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic Description | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic Notes | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic RiskFunction | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic RiskId | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic RiskOn | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic Links Description | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic Links Notes | NA | NA | Risk Input - Probabilistic Links Notes | NA | NA | NA | NA |
Risk Input - Probabilistic Links RiskFunction | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic Links RiskId | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Probabilistic Links RiskOn | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Task Existence Description | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Task Existence Notes | NA | NA | Risk Input - Task Existence Notes | NA | NA | NA | NA |
Risk Input - Task Existence RiskFunction | NA | NA | Risk Input - Task Existence Function | NA | NA | NA | NA |
Risk Input - Task Existence RiskId | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Task Existence RiskOn | NA | NA | Calculated | NA | NA | NA | NA |
Risk Input - Task Existence Probability | NA | NA | Risk Input - Task Existence | NA | NA | NA | NA |
Risk Output - CostSensitivity | NA | NA | Risk Output - CostSensitivity | NA | NA | NA | NA |
Risk Output - CostStdDeviation | NA | NA | Risk Output - CostStdDeviation | NA | NA | NA | NA |
Risk Output - CriticalityIndex | NA | NA | Risk Output - CriticalityIndex | NA | NA | NA | NA |
Risk Output - DurationCruciality | NA | NA | Risk Output - Duration Cruciality | NA | NA | NA | NA |
Risk Output - DurationStdDeviation | NA | NA | Risk Output - DurationStdDeviation | NA | NA | NA | NA |
Risk Output - DurationSensitivity | NA | NA | Risk Output - DurationSensitivity | NA | NA | NA | NA |
Risk Output - MeanCost | NA | NA | Risk Output - MeanCost | NA | NA | NA | NA |
Risk Output - MeanDuration | NA | NA | Risk Output - MeanDuration | NA | NA | NA | NA |
Risk Output - MeanFinish | NA | NA | Risk Output - MeanFinish | NA | NA | NA | NA |
Risk Output - MeanStart | NA | NA | Risk Output - MeanStart | NA | NA | NA | NA |
Risk Output - PercentageTaskExisted | NA | NA | Risk Output - % Iterations Existed | NA | NA | NA | NA |
Risk Output - ScheduleSensitivityIndex | NA | NA | Risk Output - ScheduleSensitivityIndex | NA | NA | NA | NA |
Secondary Constraint | NA | Secondary Constraint | NA | NA | Calculated | Secondary Constraint | Calculated |
Secondary Constraint Date | NA | Secondary Constraint Date | NA | NA | Calculated | Secondary Constraint Date | Calculated |
Start | Start | Start | Start | Start | Early Start | CurrentScheduledBasePeriod.Start | Calculated |
Total Cost | Cost | Calculated | Cost[Total] | NA | Calculated | NA | NA |
Total Float | Total Slack | Total Float | TotalFinshFloat | NA | Total Float | ProjectScheduleTask.TotalFloatDurationMeasure | Total Float |
WBS Code | Outline Number | WBS | Work Breakdown Structure | WBS Code | NA | NA | NA |
WBS Name | Outline Number | WBS Name | Work Breakdown Structure | WBS Name | NA | NA | NA |
WORST | NA | NA | NA | WORST | NA | NA | NA |