Add Activities to the Timeline View
Add activities to the Timeline view. This is useful when looking at the big picture within a project as well as comparing a project to its respective snapshots or scenarios.
To add activities to the Timeline view, complete the following steps:
- Select the S1 // Projects tab.
- In the Activities group, click Activity View.
-
To assign activities to the timeline, do one of the following:
- To select individual activities, use the check boxes in the Activity view list.
- To select all activities within a group, select the check box next to the parent activity.
- In the Activities group, click Timeline View. Each project/snapshot/scenario is shown in its own timeline.
- (Optional) In the Activities group, click the Timeline View drop-down arrow to use the Timeline View options.