Use the commands in this group to create a cost estimate in order to perform a cost risk analysis. You can then generate charts against cost models.
Create Cost Estimate
Click this icon to create a new cost estimate in Acumen or use the drop-down menu options to create or import cost estimates.
Field | Description |
Create Cost Estimate
|
Click this option to create a new cost estimate.
|
Generate From Schedule
|
- Generate With Overlay — Select this option to overlay every activity in the cost model to every activity in the schedule.
- Generate Without Overlay — Select this option if you do not want any cost and schedule overlay.
|
Import cost estimate using Excel
|
Click this option to import an existing cost estimate from MS Excel.
|