Microsoft Project
Acumen allows you to link to and import data from Microsoft Project, Microsoft Project Server, and Project Online (the hosted version of Project Server).
With Microsoft Project, Acumen links to Microsoft Project (MSP) files using your installed copy of MS Project or by directly reading an .MPP file (without needing MS Project installed on your computer).
With Microsoft Project Server, Acumen downloads the project data from the Project Web App (PWA) site into Acumen. With Project Online, Acumen downloads the Project Server project data from the hosted (Office 365) server. After you import the data, you can view the original file path on the S1 // Projects tab Activities view General tab.
- Cost, schedule, risk, and earned value integration by default.
- Custom field mapping (normal, code, and user-defined fields).
When you import a project from Microsoft Project, Acumen also imports the Estimated and Manual fields.
Exporting an Acumen Project as a Microsoft Project XML File
When you export an Acumen project as a Microsoft Project XML file, any existing user-defined fields are included in the export and are available for use in MSP.
Exporting a Master Project Scenario as a Microsoft Project MPP File
You cannot export a master project scenario as an .MPP file.
Microsoft Project Platform Options
- Web Service Timeout — Set the number of seconds before the Microsoft Project Server web service times out. The default is 300 seconds.
- Return Project Codes in Project Picker — When you import Microsoft Project Server, importing the code assignments can take additional time for a large project. In order to improve performance, you can specify whether the system should retrieve project code assignments when you import an MSP Server project list. If selected, the code assignment columns display in the grid on the MSP Server Project Selection dialog box (used when importing a project). It is not selected by default.
- Server Type: Select the server version that you are using. If this version is different from the Project Server version that you import, you may have some data discrepancies.
If you change this setting, you must close and restart Acumen for the change to take effect.
Standard Field Mappings
- Physical % Complete: The Physical % Complete field is auto-mapped to the Microsoft Project Physical % Complete field.