Remove a P6 baseline from a P6 Schedule

Use these steps to remove an existing P6 baseline from a P6 schedule.

To remove a P6 baseline from a P6 schedule, complete the following steps:

  1. Select the S1 // Projects tab.
  2. Do one of the following:
    • In the Projects pane, right-click on the P6 project and select Clear Baseline.
    • Select the P6 project in the Projects pane then, in the Get External Data From group, click Oracle Primavera > Clear Baseline.
    The baseline is removed and the black B () on the Primavera P6 file icon in the Projects panel of the workbook no longer displays.