Remove a P6 baseline from a P6 Schedule
Use these steps to remove an existing P6 baseline from a P6 schedule.
To remove a P6 baseline from a P6 schedule, complete the following steps:
- Select the S1 // Projects tab.
-
Do one of the following:
- In the Projects pane, right-click on the P6 project and select Clear Baseline.
- Select the P6 project in the Projects pane then, in the Get External Data From group, click .